Accelerated Loss of Mains Change Programme (ALoMCP)

Generators with a G59 relay installed before February 2018 must get them updated by September 2020. Those that act now can get  access to funding for the update carried out free of charge.

Sign Up Here


*** LIMITED TIME OFFER SO ACT NOW ***
Next window is closing 11/02/2020

How it Works

1. Get in touch
Either give us a call or fill out our contact form and we will be in touch with you as soon as possible to discuss your upgrade application.

2. Send us a copy of your G59 witnessed test report
If we are able to help, we will request your witness test report to enable check your eligibility. 

3. Our engineers perform the upgrade
We will arrange a time to perform the upgrade. An engineer will visit your site and perform the necessary changes.

4. Free upgrade
We won’t charge you anything — the application, works, and verification will be free of charge!

Regulation changes

Generation owners are required by the Distribution Code to install loss of mains (LoM) protection at distributed generation sites. 

This is to ensure that, following a fault that isolates sections of the distribution system to which they are connected from the rest of the electricity system, distributed generation does not form an autonomous power island with the remaining local demand.

Generators associated with the system after February 2018 that as of now use G59 should be upgraded to G59/4. 

The explanation behind this update is due to the Loss Of Mains protection for existing Renewable Energy Generators. One of the fundamental advantages of this is to decrease the amount of tripping by relaxing the RoCoF limits.

Window Start End Duration
Window 1 2nd Oct 2019 11th Nov 2019 6 Weeks
Window 2 13th Nov 2018 11th Feb 2020 3 Months
Window 3 12th Feb 2020 12th May 2020 3 Months
Window 4 13th May 2020 11th Aug 2020 3 Months